Electrical Maintenance North Campus - Monday, 15th March 2021

Wednesday, March 10, 2021 - 16:00
The North Campus electrical distribution system requires annual maintenance and to do this the electrical supply to the campus will be off for approx. 3-4 hours. 
 
We have scheduled this maintenance for Monday the 15th March at 4am. The shut down would be from 4am until 8am approx.. 
 
The timing is during study week so it will not impact lectures and early in the morning so that staff (maintenance and departmental technical) would be in to address any issues that may arise following the shutdown. 
 
I would expect that the maintenance on the initial sub stations to be complete in three hours and power restored with the remaining sub stations completed in the following hour. 
 
This will affect the North Campus only, the South Campus will not be affected. 
 
If you have any issues regarding this please contact [email protected] that we can address your concern.